Key takeaways
The risk after direct sourcing is not capability but the seam. Four criteria decide who tests what and how far - where the condition comes from, where the failure would surface, where process control sits, and who reads the report. Three parameters on the seam (how stress is applied at the interface, the sample state, and the acceptance grade) must be owned by one party and written into both reports; otherwise every party passes on paper while the vehicle assembly fails.
The most common misjudgement after an OEM moves to direct sourcing is "there is less work for us". Fewer orders, fewer samples and fewer tests is not what happens. What changes is which layer the constraint sits at. Previously the OEM handed the specification to Tier1, and Tier1 broke it down one level further. Now the OEM may bypass the middle layer and hold the drawing, the sample sign-off and the production-consistency gate itself, while condition detail and process control stay where they were. One specification therefore becomes two reports. Each is compliant on its own, and nobody owns the seam.
1. What direct sourcing actually changes
Set the commercial benefits aside and look only at structure. In testing terms, direct sourcing performs three moves:
- Condition ownership moves up. The specification comes from the OEM, and nobody can "agree a level with the tier above" any more.
- The sample sign-off threshold moves up. Whosever part enters the vehicle has to be independently verifiable by the OEM.
- The gatekeeper for production consistency changes. Previously it watched Tier1 shipments; now it may look directly at the process capability of the sub-part supplier.
None of the three touches testing itself. What changes is the direction of report flow: reports no longer run in one line downwards but may run as two parallel streams addressed to different readers.
That is where the seam comes from. One specification, two executing parties, two report streams, and a few blank fields left on the seam. While nothing goes wrong, no one notices. When something goes wrong, both sides were compliant.
2. Three layers: constraint, execution, verification
Splitting the work by who defines, who performs and who judges makes the problem much clearer:
| Layer | Owner | Main content | What happens if it is left empty |
|---|---|---|---|
| --- | --- | --- | --- |
| Constraint | OEM | Drawing and specification revision, mounting location and temperature class, functional status grade, critical characteristics | Each party infers its own, and peer parts end up with two condition sets |
| Execution | Tier1 or Tier2 | Test plan, sample state and fixturing, measurement and monitoring points, process control | Data exists but cannot be attributed to an owner |
| Verification | OEM or its designated laboratory | Sample confirmation, sampling, production consistency, change verification | The conclusion covers the sample only, not the batch |
The boundary is drawn by decision authority, not by contract tier. One company can occupy more than one layer at once - and that is often exactly the problem: it executes and verifies its own work, so a difference on the seam never gets raised.
To decide which layer an item belongs to, ask one question: if the executing party changed this field by itself, would the vehicle-level acceptance verdict change? If yes, it belongs to the constraint layer. Only if not may it be delegated.
3. Four criteria for drawing the split
No debate is needed; run each item through four criteria:
| Criterion | Question | Tendency |
|---|---|---|
| --- | --- | --- |
| Condition ownership | Is this level set by the drawing, or chosen by the executor from experience | Drawing-set goes to the constraint layer |
| Failure ownership | If this item fails, at which level is the failure first seen | Seen first at assembly means Tier1 |
| Process ownership | Whose production line holds the parameter that decides this item | Whoever holds the line owns the item |
| Report reader | Who signs off on the benefit of this page | Whoever signs the sample confirmation |
The fourth is routinely ignored. A report is written for its reader, not for its author. A report used by the OEM for sample confirmation and a report used internally to tune a process may carry the same title and the same data, yet the verdict fields should read differently: the first has to stand alone, the second may carry qualified statements.
Running the four criteria usually produces three groups: items Tier1 must perform, items that can be delegated to Tier2, and items both sides perform but on one shared parameter. That third group is the seam, and it is the one most often skipped.
4. Three parameters on the seam need one owner
The seam is not a vague communication problem. It has a concrete shape. Three parameters decide whether it holds:
How stress is applied at the interface. Once a sub-part is assembled, the direction of the stress, the way it is restrained and the heat path all change. The same vibration spectrum applied to a bare part and to a built assembly acts at different points and excites different modes. If Tier2 reports the bare part as acceptable and Tier1 reports the assembly as acceptable, the segment in between - what the stress becomes after assembly - belongs to nobody.
The sample state. Powered or unpowered, under what load, with or without the harness, with or without the heat-sink structure. This field is often worded similarly in both reports and means something different in each. Read side by side they look like one thing and are actually two different tests.
The acceptance grade. Functional status grade, permitted deviation, whether self-recovery is allowed. Judging the same product at different grades across layers is the most common seam mismatch: the assembly level permits a degradation that the sub-part level grades at full, so the sub-part report gets returned first; the reverse case passes the sub-part and fails the assembly, followed by two weeks of investigation that ends at a difference in wording.
There are only two correct attitudes. Either one party owns the three parameters and writes them into both reports, or both reports state explicitly that the other party's basis differs and attach the difference. What cannot be accepted is each side following its own habit and meeting for the first time at the review table.
5. Five questions to open the review
If the project is already running and the responsibility map cannot be redrawn, take these five questions into the next review. They do not fix capability, but they locate the seam:
- Which document and which revision did this condition originally come from?
- If this item fails, at which level and which step is it first seen?
- Whose site holds the process that decides this item?
- Is the sample state in the two reports describing the same thing?
- Who set the acceptance grade, and on what basis?
Projects that answer all five clearly usually need no extra testing. Projects that cannot answer the third and the fifth have a supplier-management problem, not a laboratory problem.
6. Validity limits of the two report types
Direct sourcing multiplies reports, but each one's reach does not grow. Keep the two types apart:
- The sub-part (Tier2) report records facts: this part, under this condition set, produced these readings. It can go straight into change approval and batch traceability, because it records reproducible inputs and outputs.
- The assembly (Tier1) report records a verdict: an assembly built this way is or is not acceptable in vehicle context. It carries a judgement, and a judgement depends on conditions, fixturing and monitoring. Change those and the verdict no longer travels with the part.
The reverse is also true: an assembly report does not replace a sub-part report, and sub-part reports do not simply add up to an assembly conclusion. That sounds obvious, yet in direct-sourcing programmes it is treated as paperwork and skimmed over - because the two documents look alike, readers assume they say the same thing.
For where conditions themselves come from, three companion articles help: why OEM standards are stricter than national ones, how a German OEM standard relates to the ISO framework, and what "passed" really covers when a part fails after assembly - the last is the same seam question seen from the other side. Together with ISO 16750 and GB/T 28046 they form the chain from "what the standard provides" to "who passes it down".
The items executed at the lower layer still come back to specific laboratory capability: on the EMC side, how electromagnetic compatibility testing arranges set-up and grades; on the mechanical side, how mechanical load criteria are defined. These two are where "both sides tested, with different conditions" most often happens under direct sourcing. Checking the basis against these two pages before a review is faster than reading every report line by line.
A few plain words
After direct sourcing the expensive thing is not one more test, it is an unowned seam. Handling a seam parameter once costs a few samples and some schedule. Skipping it and discovering it at vehicle level costs the project timeline.
For executing parties there is one piece of advice: state precisely what you own, including what you do not. A report that openly says "this does not cover interface stress after assembly" survives review better than one that claims everything is acceptable.
For purchasing and quality teams there is also one: write the seam parameters into the purchasing terms, not just the standard numbers. The standard numbers decide which items are performed; the seam parameters decide whether those items form one evidence chain.
Scheduling is arranged per project; you can state your expected delivery date when submitting samples, and we will confirm a feasible plan against the current schedule and report progress at each milestone.



