  4. Moving the Same Line to a New Plant - Five Quantities That Decide Which Tests Must Be Re-run

Moving the Same Line to a New Plant - Five Quantities That Decide Which Tests Must Be Re-run

Key takeaways

Whether an existing report carries over after a plant move depends on process equivalence, not on document identity. Five quantities do not travel with the equipment - utilities, building environment, the second set of tooling and moulds, people and shifts, and the measurement system - yet all five sit on failure paths. Scope follows process sensitivity by operation family: interface-forming and material-state-changing steps make it a different product, assembly and fastening steps need key items repeated, pure assembly and packaging needs sampling only. Write the file in five columns - change list, impact analysis, re-run and bridging set, first-batch tightening, and release conclusion with its boundary. Skip the last two and problems return from the customer side.

The hard question after a plant move is not whether to retest. It is how you justify calling it the same process. Drawings unchanged, BOM unchanged, process parameters untouched word for word, and the existing report still cannot simply be carried over. What made that report valid was the controlled variation behind the documents, and moving the shop floor changes that variation first. Relocation, duplicating a line inside the same plant, splitting production across two sites, and outsourcing a single operation do not move the same thing, so the re-run scope should not be a single template either.

A boundary first: this article covers only what happens to existing part-level test reports after the production site or line changes, and which items have to be added. Material substitution belongs to a different line - see which tests must be repeated after a chip swap. Whether a report expires with time is also a separate topic.

1. Four kinds of change move different things

Companies usually file all four under one word and route them through one approval form. On the testing side their risk lands in completely different places.

Change typeWhat actually movesWhere the risk lands for report carry-over
---------
Full plant relocationEquipment travels; utilities, building environment and people all changeEnvironmental and interface tests, especially welding, crimping, coating and moulding
Duplicated line in the same plantA second set of equipment and tooling built to the same drawingsDifferences between the two tooling sets; batch-to-batch consistency
Split production across sitesThe same part supplied from two locations in parallelComparability of the two sites; which site the report is responsible for
Outsourced operationOnly one process step is moved outThe interface formed by that step, plus handover to the steps before and after

The first two are especially easy to underestimate, because "the machines did not change" sounds like nothing changed. Equipment is the part of a process that can be packed and shipped. It is not the whole process.

2. Five quantities that do not travel

What goes into the crates is the machines, the drawings and the parameter sheets. What stays behind is the following five.

QuantityWhy it does not travelWhere it shows up in testing
---------
UtilitiesVoltage fluctuation and harmonics, earthing resistance, compressed-air dew point and oil content, water quality and pressure, all set by the site networkInterface quality in welding and crimping, coating adhesion, abnormal resets under electrical loads
Building environmentAnnual temperature and humidity swing, cleanliness, floor vibration, distribution of sunlight and equipment heatDifferent starting points in climatic tests, geometric deviation in precision assembly
Second set of tooling and mouldsTwo sets built to one drawing differ in datum, wear state and thermal balanceFirst-article dimensions and appearance, sealing and insertion force, batch-to-batch spread
People and shiftsNew site, new operators, re-timed takt, changed self-inspection frequency and judgement habitsBatches with poor consistency, drift in how strictly appearance criteria are read
Measurement systemCalibration chain, gauges and fixtures, version of the measuring programEvery item judged from a reading, including process capability data

None of the five appears on a drawing. None of them appears in the BOM. All of them sit on failure paths. Matching drawings proves the design did not change; it does not prove the process did not.

One point that is often missed: the second tooling set is not a copy. Two moulds built to one drawing differ in gate position, cooling circuit and guide-pin wear, and two fixtures differ slightly in datum. That difference is invisible on a single part and shows up in the batch distribution.

3. Scope follows process sensitivity

There is no need to repeat every item, and sampling appearance and function alone is not enough. The criterion is whether this operation writes the process into the product.

Operation familyProcess sensitivityMinimum action before a report is carried over
---------
Interface forming (welding, crimping, bonding, coating, moulding)High: interface quality is a direct function of process parametersRe-run or bridge the interface items, including coating-to-substrate adhesion and weld penetration and failure location in plastic welding
Material state change (heat treatment, stress relief, drying, curing)High: what comes out is not the same state that went inMechanical properties and post-vibration re-measurement, then interface re-checks after climatic exposure
Assembly and fasteningMedium: torque and preload are controlled, but the tooling changedRe-measure preload and sealing, re-measure contact resistance after vibration
Pure assembly, packaging, markingLow: the process does not change the physical state of the partFirst-article confirmation plus consecutive-batch sampling; no type-test repetition

The judgement collapses into one line: wherever the process changes material state or interface morphology, a new address means a new product. For the rest, what changed is management, not the product.

The third column says "re-run or bridge" because the two routes do not carry the same weight. Re-running walks the full set of conditions again; bridging tightens the few items that can expose this particular change. Bridging costs less, but it only holds when the change list is complete - miss one item and bridging degrades into sampling. How bridging conclusions get accepted follows the same "do four things line up" check used in accepting subcontracted test reports.

4. Write the scope as a file someone can execute

"Requalification complete" and "these items were repeated, these were not, and here is why" are two documents of very different credibility. Five columns are enough.

ColumnWhat goes in itWhat happens if it is missing
---------
Change listAddress, utilities, number of tooling sets, people, measurement system - changed or not, item by itemImpact analysis has no starting point; review runs on impressions
Impact analysisWhich failure mode each change touches, and whether it worsens, eases or is irrelevantScope becomes a guess; neither strict nor loose can be defended
Re-run and bridging setItem name, standard version, criteria grade, and the link to this changeThe customer asks for everything; cost and elapsed time both go up
First-batch tighteningMonitoring items for first article and consecutive batches, criteria, and what to do on an anomalyProblems come back from the customer side two or three months later
Release conclusion and boundaryWhich site, which line, which drawing revision the conclusion covers, and what triggers the next changeThe report gets used somewhere it never covered

The fourth column is the one usually dropped, and post-move problems tend to appear in the third or fourth batch rather than the first - tooling wear, parameter drift and operator familiarity all need time to show. A clean first article does not mean the process has settled. The three inspection layers used in volume production apply directly here: the first article answers whether the part can be built, consecutive batches answer whether it can still be built the same way.

The fifth column matters as much. A report stating it applies to plant A, line 2, being used to support shipments from plant B is a frequent overreach in this kind of project. The validity boundary belongs inside the report, not in someone's memory.

5. Straight talk

Relocation, line duplication and outsourcing save money on the cost sheet and bring risk forward on the quality ledger. Whether the saving survives depends on how carefully the requalification was done.

Do the impact analysis before fixing the scope. The reverse order is common - pick a few items by experience, test them, then write a note that makes the conclusion fit. Such a file rarely survives two rounds of customer review.

One more: do not let "it is the same line" replace a change description. A line can be dismantled, crated and rebuilt at a new address, and the rebuilt line shares nothing with the old one except equipment serial numbers.

Conditions and criteria still come first. GB/T 28046 and ISO 16750 provide application conditions and functional status grades, while CISPR 25 provides emission limits and measurement layout. None of them will decide whether a relocation needs a re-run; that decision rests on the change list and the impact analysis. When TMC LAB takes on requalification after such a change, the change list and re-run scope are turned into a test plan first, and individual test items are scheduled after that.

As for whether a partial requalification is acceptable: yes, provided the part selected actually covers this change. Whatever it does not cover is sampling, no matter how many items are run.

Scheduling is arranged per project; you can state your expected delivery date when submitting samples, and we will confirm a feasible plan against the current schedule and report progress at each milestone.

Related Q&A

Related questions

Frequently asked questions on the same topic. The first paragraph of each answer is the conclusion.

After moving to a new plant, can we just do appearance and functional sampling and keep the existing reports?
Usually not, unless the product passes through no interface-forming operation at all. Appearance and functional sampling catch obvious defects; what they do not catch is a change in interface quality. Weld penetration, crimp compression, coating adhesion and weld lines in moulded parts are all functions of process parameters. Testing shows the result, not the margin. After a move the margin may have shrunk while sampling still passes, and the difference surfaces after humidity cycling or vibration. To carry a report over, complete the change list, re-run or bridge the interface items, and state the boundary within which the conclusion applies.
If the same machines are moved unchanged into a new building, is that a process change?
Yes. Equipment is the part of a process that can be packed and shipped, not the whole process. What travels is the machine, the drawings and the parameter sheets. What does not travel is the utilities (power quality and earthing, compressed-air dew point, water quality and pressure), the building environment (annual temperature and humidity swing, cleanliness, floor vibration), the second set of tooling and moulds, the people and shift pattern, and the measurement system. None of these appear on a drawing, yet all of them sit on failure paths. The question is not whether the asset number changed, but how far these quantities differ at the new address and whether the difference touches the conclusion you want to carry over.
The customer wants every test repeated. Can we argue for bridging tests only?
Yes, provided the change list and impact analysis exist. The strength of a bridging programme comes from correspondence: each repeated or tightened item must point to a specific failure mode affected by this change. With a complete list the bridging scope is arguable. With an incomplete list, bridging degrades into sampling and the customer's demand to repeat everything is reasonable. In practice, submit three parallel columns - items to repeat, items to bridge, and items not repeated with reasons - so the reviewer can see where the boundary lies instead of a conclusion page stating that requalification is complete.

These answers share the same data source as the FAQ page.

Have a testing requirement? Send us your product details

Tell us the product model and test requirements. Our engineers will map out the test plan, the applicable standards and the item combination, and provide a quotation reference. The more specific the request, the sharper the answer.

  • Free scoping of the test plan and standards
  • Pre-scan testing during R&D to cut rework cost
  • On-site visits and witnessed testing supported
  • Scheduling per project, with progress updates at each milestone