Key takeaways
An interruption does not undo the stress already delivered to the sample, so how long the gap lasted is not the criterion. The criterion is whether the interruption introduced a new stress in a different direction, or an irreversible change of state. Each of the four types leaves something different behind: an inrush on power restoration, condensation, a shifted accumulation baseline, or an excitation that was already out of tolerance. Making up the time restores the duration, not what already happened. In damp heat, thermal cycling or salt spray, opening the door once adds a condition the test plan never specified. Check whether the sample changed first, whether the excitation can be trusted second, and the duration gap last.
Whether an interrupted test has to start over does not depend on how long the gap lasted. An interruption does not roll back the stress already delivered to the sample. What decides the outcome is what the sample went through at that moment: whether a new stress in a different direction was introduced, or an irreversible change of state took place. A power cut, an opened door, a re-clamped fixture and a shaker alarm each leave something different behind, and they should not be handled the same way.
Clients usually ask a single question — the run stopped for two hours, must it be repeated? That question leaves out three things: whether the chamber conditions drifted, whether the sample was powered, and what was confirmed before resuming. With any of the three missing, every answer is a guess.
1. Separate the three time segments
In the segment before the interruption, change has already happened. Ageing at the material level, accumulated damage, diffusion across an interface — none of it reverses because the run is repeated later. That segment is sunk, but it is also valid, provided the conditions really were applied as specified at the time.
The moment of interruption is where every judgement diverges. The same ten-minute stop means two different things depending on whether the power was cut or the door was opened; unloading a shaker and a chamber over-temperature alarm are two further different things.
The segment after the interruption restores duration and restores conditions. It does not restore what happened in between.
Making up the time restores the duration, not what already happened. That sentence is the backbone of the whole judgement. Any approach that treats a topped-up duration as a completed test has skipped the middle moment.
2. Four kinds of interruption leave different things behind
| Interruption | What the sample went through at that moment | What cannot be undone by repeating |
|---|---|---|
| --- | --- | --- |
| Power loss | The sample drops out and sees an inrush on restoration: surge, power-up sequencing, initialisation and spurious outputs; in a temperature test a cold start is added on top | The electrical and functional trace left at restoration, plus any drift in conditions while the power was off |
| Door opened for inspection | The chamber temperature changes abruptly; a cold part meeting humid air condenses on its surface, a hot part meeting cooler air draws moisture in through the pressure difference | The condensation and moisture uptake that already occurred, and the corrosion or leakage starting point it created |
| Shaker stopped and re-clamped | Fixture position and clamping force change, the relationship between control point and response point may change, and the damage-accumulation baseline moves with it | The damage accumulated under the original clamping, which can no longer be summed with the later segment |
| Alarm or out-of-tolerance stop | In the segment before the alarm the excitation may already have been outside tolerance, with nobody watching | The stress actually applied during that segment, which is not the stress the test plan specifies |
The second row is the one most often dismissed as harmless. A look inside, a photograph, nudging the sample — small motions, but in damp heat and thermal cycling they change the phase of water on the surface. Why a housing draws moisture in after a temperature swing is broken down in a separate article on pressure equalisation and breathing; see sealed housing pressure equalisation.
The fourth row deserves its own sentence: an alarm is an effect, not a cause. In the segment before the alarm the reading may have been running outside tolerance for a while, with the threshold simply not yet crossed. Handling an alarm-type interruption therefore means going back to the curve before the alarm, not counting only from the moment it sounded.
3. Where the three verdicts divide
| Verdict | When it applies | Where the cost lands |
|---|---|---|
| --- | --- | --- |
| Continue with the balance | No new stress introduced, no change of state, the accumulation basis can be joined up, and the self-check before resuming was normal | Only chamber time is extended; the premise is a complete record, otherwise the position cannot be defended later |
| Redo that segment | The interruption left a stress in a different direction, or the excitation during that segment cannot be trusted | The duration of that segment is lost, but less than a full repeat — provided the segment boundary can be defined |
| Void the run | The interruption changed the sample's initial state: condensation or frost, re-clamping followed by refitting, the sample having been taken apart | The whole run is lost and has to be rescheduled; expensive, but the conclusion is clean |
Argument usually lands on the middle verdict, and specifically on where "that segment" begins. A workable approach anchors it to an observable event: the last reading confirmed in tolerance, the last node at which the self-check passed, or the last sample inside tolerance before the alarm. If the anchor can be written down, the segment can be bounded. If it cannot, the practical result is a voided run that nobody wants to call by that name.
Fix the order of judgement as well: check whether the sample changed first, whether the excitation can be trusted second, and the duration gap last. In the reverse order the discussion becomes a contest of volume rather than of data.
4. A four-column interruption clause for the test plan
| Column | What it should state | What happens without it |
|---|---|---|
| --- | --- | --- |
| Permitted interruptions | Which interruptions may be continued through (a planned mid-run inspection, a sensor swap) and which are treated as invalid outright (power loss, over-temperature, an opened door, the sample being moved) | The operator decides on the spot, and the same laboratory handles the same event differently twice |
| State confirmation before resuming | What to do first: stabilise or dry, inspect, run functional self-checks, re-measure key parameters, and what each of those decides | The run is resumed directly and the drift during the gap is written into the result |
| Line between topping up and redoing | Which anchor defines the segment, and from which point the accumulated duration resumes | The dispute is settled by negotiation, and the outcome depends on the relationship rather than the data |
| Record and notification | Who records, what is recorded, when the client is informed, and whether the client must confirm | The interruption surfaces only when the report is issued, leaving the client to accept it or repeat everything |
Writing those four columns costs little — usually one conversation before the chamber is loaded. What it buys is a basis for the people standing at the equipment when something stops. How decision criteria themselves are set, and how boundary readings are handled, is a separate thread covered in decision rules and boundary readings.
5. Five record items in the report
| Item | What to record | What goes missing without it |
|---|---|---|
| --- | --- | --- |
| Time and duration | The accumulated point at which the interruption occurred and how long it lasted | The total duration loses traceability and becomes an isolated number |
| State at the moment | Whether the sample was powered, whether the door was opened, the actual chamber readings | The judgement loses its basis, and a harmless stop cannot be told from a changed state |
| Cause | Supply, equipment, human action, or an anomaly in the sample itself | There is no way to judge whether the same event will recur |
| Confirmation before resuming | The conclusions of stabilisation, drying, visual inspection, functional self-check and parameter re-measurement | Drift during the gap is folded into the result and cannot be seen in the report |
| Accumulation basis afterwards | From which point the run resumed and how the two segments were added | The accumulation method is unclear and the figures do not line up against another laboratory |
Readers of reports should use these items too. A missing interruption record and a missing tolerance record are two different problems: the first says the history cannot be told, the second says the excitation itself is in doubt. How to read both in a random vibration report is covered in more detail in the article on reading a PSD: reading a random vibration PSD.
6. A few plain words
An interruption is not the problem; an unrecorded one is. Laboratories that have run thousands of tests still trip breakers and still find loose sensors. The difference is whether something was left behind that can be reviewed.
Do not treat a topped-up duration as a completed test. Topping up answers the duration column. What happened to the sample is a different column.
Fixing the order of judgement is more useful than fixing a uniform threshold in minutes. Thresholds are counted in minutes; what happens inside a sample is not.
In damp heat, thermal cycling and salt spray, one door opening belongs in the record. This is among the more common omissions seen in real commissions, and the one most easily blamed on something else in later judgement.
Test scheduling itself carries interruption risk, particularly when one chamber serves several lots at once. When TMC LAB handles this kind of commission, the four-column clause and the five record items are confirmed before the chamber is loaded, written into the plan alongside the profile and the acceptance criteria rather than negotiated after something stops.
How the conditions themselves are arranged and sequenced is covered separately; the combination of the five climatic stresses is set out in GB/T 28046.4 climate load combination, and the way the two document families specify conditions is broken down clause by clause on the standards pages for GB/T 28046 and ISO 16750. For commissions that need interruption handling written into the plan, the service pages on environmental reliability testing and temperature cycling set out the working basis.
Scheduling is arranged per project; you can state your expected delivery date when submitting samples, and we will confirm a feasible plan against the current schedule and report progress at each milestone.